Drainage that wasn't in the takeoff
01Situation
Framing takeoff did not account for drainage of a prefabricated balcony. Technical info existed — balcony has drainage — but didn't reach the person doing takeoff.
02Where Margin Escaped
Collision and rework at a stage when scope is already priced and partially executed. Rework cost wasn't in any item — so it eats up the margin of neighboring items.
03Root Cause
Incomplete input at planning stage. Not lack of knowledge — lack of knowledge flow to the right moment: the takeoff.
!How we aim to close it
Each such case could stay in the system as a checkpoint, and for a similar scope the takeoff checklist would prompt: “prefab balcony — drainage accounted for?”. This is a direction; today Desk supports survey tasks (photo documentation and takeoff) without checklists.
Read Next Story
Flashing after cladding: double work and a cracked panel
Poor sequencing means work is done twice. And damage without attribution dissolves into 'overhead costs'.
The day that cost two days
An assignment described in one sentence: 'stones to lay on the roof'. Three people knew what that roof was coated with. None of them tied it to who was going up there. One sentence didn't travel — and one day cost two.